Customer request:
Increasing the draw-off of the fourth vacuum side cut from column K-5 of the CDU/VDU-6 unit and improving its quality (reducing the colorimeter colour reading) while increasing the tar viscosity to approximately 300 mm²/s or higher,
Improving fractionation sharpness and optimising operation of the wash section in vacuum column K-5 of the CDU/VDU-6 unit.
Spliteks solution:
-
Modelling column operation based on actual operating data
-
Report and recommendations on changing the column operating mode and partially replacing the column internals
-
Engineering
-
Manufacturing at the facility in Serpukhov
-
Delivery of the batch to the customer’s site
-
Installation supervision at the customer’s site and advice during commissioning